« 31 December 20121 January 2013 2 January 2013 »
Time | Event | Location | |
---|---|---|---|
09:00 – 12:00 | Purchasing Process:Step #4 Approvals | ||
09:00 – 13:00 | Purchasing Process:Step #6 Post Award Administration & Payment Policy | ||
09:00 – 11:00 | Purchasing Process:Step #1 Initiate Buy | ||
09:00 – 12:30 | Purchasing Process:Step #3 Taxes - LIGO Ops | ||
09:00 – 10:30 | Purchasing Process:GSA is not authorized | ||
09:00 – 09:30 | Purchasing Process:No Longer Maintained - Purchasing Schedule Tracking Metric for LIGO Ops 2013 | ||
09:00 – 12:30 | Purchasing Process:Step #3 Documentation & Requisition | ||
09:00 – 10:00 | Purchasing Process:Advanced LIGO Reference Docs on Hold | ||
09:00 – 09:30 | Purchasing Process:Purchasing Process LIGO Ops 2013 | ||
09:00 – 09:30 | Purchasing Process:Step #5 Award PO | ||
09:00 – 17:30 | Purchasing Process:Step #2 Supplier Selection |
DCC Version 3.5.0, contact
DCC Help