LIGO Document E1200510-v1

aLIGO HAM-ISI, Pre-Installation Test Report, Phase II, LHO HAM 6

Document #:
LIGO-E1200510-v1
Document type:
E - Engineering documents
Other Versions:
Abstract:
Camber-side Testing (pages 5 to 13)
------------------

The Chamber SIde Testing was performed on HAM3-ISI between July 1st and July 3rd 2013.

All sensors appeared to be functional. Serial numbers were recorded.

In-Chamber insertion was performed on July 11th 2013. Initial In-Chamber Testing will follow.

Topics:
Authors:
Referenced by:

DCC Version 3.4.2, contact Document Database Administrators