Document List by Topic

These documents on Observatory Facilities (subtopic of Detector) are available:
(List events on Observatory Facilities)

LIGO-Number Title Author(s) Topic(s) Last Updated
C1106833-v2 SOW LHO Landscape Maintenance and Tumbleweed Removal John Worden et al. Operations Business
Observatory Facilities
11 Sep 2015
D1003029-v1 Work Platform Example Drawing Sam Barnum et al. Requirements
Observatory Facilities
26 Oct 2023
T2300353-v1 Site Selection and Facilities Design excerpt from the GW Handbook Robert Schofield Preliminary Design
Observatory Facilities
06 Sep 2023
E2300282-v2 Acoustic Noise Spectra (Caltech) Murtaza Hathiyari et al. Operations
Observatory Facilities
28 Aug 2023
D1002704-v6 Rack and Cable Tray Layout, LVEA, H1 H2 Dennis Coyne System Engineering
Observatory Facilities
08 Aug 2023
D2100303-v1 A304 - FCES Elevations - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D2100302-v1 A303 - FCES Elevations - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D2100298-v1 A205 - Filter Cavity End Station - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D1300734-v1 aLIGO BSC Work Platform/E-Module Top Level Assembly John Worden et al. Observatory Facilities
10 Jan 2023
E1200331-x0 LLO Electronics Rack Document Tree (Snumbers) David Kinzel Installation
Observatory Facilities
18 Jan 2022
D1400148-v1 LHO LSB Floor Plan John Worden Observatory Facilities
18 Nov 2021
D2100346-v1 S103 - FC Tube Enclosure B Foundation and Slab Plan - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D2100301-v1 A302 - FCTE Overall Elevations - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D2100294-v1 A200 - Overall Plan - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D2100345-v1 S102 - Filter Cavity End Station FCES Foundation and Slab Plan - APLUS LHO Facilities Construction Drawing Index Anthony Simon et al. A+
Observatory Facilities
16 Nov 2021
D080367-v6 VIEWPORT GUARD ASSEMBLY Michael Meyer et al. Vacuum
Auxiliary Optics
Final Design
Observatory Facilities
23 Sep 2021
T2100269-v1 Comparing Wind-Driven Motion at LHO’s Corner and End Stations Between O3a and O3b Andrew Gao et al. Observatory Facilities
Seismic Isolation
12 Jul 2021
E1900261-v6 A+ Facility Modification Specification Michael Zucker et al. A+
Procurements
Observatory Facilities
16 Jun 2021
D1003141-v2 Rack and Cable Tray Layout, LVEA, L1 Dennis Coyne System Engineering
Observatory Facilities
30 Nov 2016
G1801003-v3 G1801003-Experiences with the underground facility for KAGRA Site Shinji Miyoki Observatory Facilities
25 Feb 2021
G2001785-v2 Wind Fence Analysis, All Plots and Data Andrew Gao Commissioning
Observatory Facilities
Seismic Isolation
14 Oct 2020
E0900047-v23 LIGO Contamination Control Plan Betsy Weaver et al. Cleaning
Observatory Facilities
Risk Management
17 Sep 2020
G2001484-v1 Evaluating the Effect of the Wind Fences on the Performance of LIGO’s Hanford Interferometer Andrew Gao et al. Commissioning
Observatory Facilities
Seismic Isolation
14 Sep 2020
G2000112-v1 Impact of the Wind Fences Brian Lantz et al. Commissioning
Observatory Facilities
Seismic Isolation
14 Feb 2020
T040127-v2 Cleaning Procedure for magnet wire with ML/HML insulation Robert Taylor Vacuum
Observatory Facilities
30 Oct 2019
G0900460-v1 Near Term Upgrades after Advanced LIGO Rana Adhikari Core Optics
Upgrades
Sensing and Control
Observatory Facilities
30 Jul 2019
T1900410-v1 Desired results of the Cosmic Explorer engineering study Rana Adhikari et al. Conceptual Design
Vacuum
Observatory Facilities
09 Jul 2019
T1900321-v1 Benefits of the trees around the LIGO Livingston Buildings Brian Lantz et al. Observatory Facilities
Seismic Isolation
30 May 2019
P0900155-v6 Accurate calibration of test mass displacement in the LIGO interferometers Jeffrey Kissel et al. Commissioning
Observatory Facilities
Calibration
16 Mar 2019
G1900481-v1 LIGO-India status and Calibration plans Shivaraj Kandhasamy et al. LIGO-India
Sensing and Control
Observatory Facilities
15 Mar 2019
G1800953-v1 [GWADW] Absolute Calibration of a Galactic Gravitational Wave Detector Network Jeffrey Kissel Astrophysics / Multi-messenger
System Engineering
External Collaboration
Modelling
Basic R&D
Integration
Upgrades
Sensing and Control
Preliminary Design
GW source predictions
Observatory Facilities
Calibration
12 Mar 2019
P1800304-v1 Metrics for next-generation gravitational-wave detectors Evan Hall et al. Conceptual Design
Compact Binaries
Basic R&D
Upgrades
Observatory Facilities
GW Bursts
05 Oct 2018
D1300496-v1 aLIGO FMP Tooling, Flange Protector, 72-1/4" I.D. Craig Conley Vacuum
Observatory Facilities
28 Nov 2018
G1601435-v3 Getting an A+: Enhancing Advanced LIGO Michael Zucker et al. Conceptual Design
Vacuum
System Engineering
Proposals
A+
Core Optics
Basic R&D
Collaboration
Squeezer
Sensing and Control
Observatory Facilities
Suspensions
Seismic Isolation
24 Aug 2018
C951751-v1 Civil Construction: Preliminary Design Report, DRAFT - Volume II-2, Construction Specifications (CDRL 11 and 13, DRD 05) Dennis Coyne Preliminary Design
Observatory Facilities
04 May 2018
D1300035-v1 LTS VPW LAYOUT, WASHINGTON - PLAN VIEW Dennis Coyne Observatory Facilities
25 Jan 2018
D1300733-v2 LHO Staging Building-aLIGO Facility Modification Plan John Worden et al. Observatory Facilities
27 Sep 2017
E1300450-v6 FMP Acceptance-Facility Modifications Carolyn Peterson et al. Observatory Facilities
26 Sep 2017
T1100416-v1 aLIGO ISC/IO Enclosures: Materials and Assembly Dani Atkinson Sensing and Control
Observatory Facilities
13 Jun 2017
C951653-v1 LIGO Technical Foundation Analyses: Executive Summary and Discussions Dennis Coyne Final Design
Observatory Facilities
01 Jun 2017
D1002509-v1 H2 Electronics building - concrete work John Worden et al. Procurements
Observatory Facilities
03 May 2017
D1003017-v1 H2 Electronics Modular Building Electrical Plan John Worden et al. Observatory Facilities
03 May 2017
D1100814-v2 H2 Electronics Building HVAC Plan John Worden et al. Observatory Facilities
03 May 2017
D1003016-v1 H2 Electronics Modular Building Plan John Worden et al. Observatory Facilities
03 May 2017
D1300361-v2 Drawing for LHO Roofing bid package. John Worden et al. Procurements
Observatory Facilities
03 May 2017
E1300301-v2 Specification for LHO Roofing task. John Worden et al. Procurements
Observatory Facilities
03 May 2017
E1600022-x0 Long-Term Studies of Site Ground Motion Jeffrey Kissel Modelling
Basic R&D
Observatory Facilities
Seismic Isolation
23 Jan 2017
D1600459-v1 LHO LSB Drawings ZIP file John Worden Observatory Facilities
29 Nov 2016
T0900568-v3 Advanced LIGO PSL Installation Plan Richard Savage et al. Laser Systems
Installation
Final Design
Observatory Facilities
21 Sep 2016
E1600272-v1 HVAC / FMCS Screen shots John Worden et al. Procurements
Observatory Facilities
29 Aug 2016
D080365-v6 Viewport Guard Michael Meyer Vacuum
Final Design
Observatory Facilities
19 May 2016
G0900710-v1 LIGO Livingston aerial oblique photo 9 Joe Giaime Public relations
Observatory Facilities
20 Feb 2016
G0900709-v1 LIGO Livingston aerial oblique photo 5 Joe Giaime Public relations
Observatory Facilities
20 Feb 2016
G0900708-v1 LIGO Livingston aerial oblique photo 1 Joe Giaime Public relations
Observatory Facilities
20 Feb 2016
G0900707-v1 LIGO Livingston aerial oblique photo 10 Joe Giaime Public relations
Observatory Facilities
20 Feb 2016
G0900706-v1 LIGO Livingston aerial oblique photo 10 cropped Joe Giaime Public relations
Observatory Facilities
20 Feb 2016
C1501447-v2 LHO Potable Water System Statement of Work Bubba Gateley Operations
Procurements
Observatory Facilities
03 Dec 2015
D1500263-v1 LLO Staging Building Bathroom Upgrade Floorplans Timothy Nelson Upgrades
Observatory Facilities
10 Sep 2015
E1500002-v2 MSR and END Station Fiber Patches Spreadsheet David Kinzel Integration
Observatory Facilities
28 Aug 2015
C1401266-v2 SOW for LLO Beam Tube Cleaning Scott McCormick Vacuum
Operations
Observatory Facilities
16 Jan 2015
D1002843-v1 aLIGO Installation, LHO X-End Station, Cartridge & Cleanroom, Layout John Worden et al. Installation
Observatory Facilities
14 Jan 2015
D1002834-v2 aLIGO Installation, LLO Y-End Station, Cartridge & Cleanroom, Layout Brian O'Reilly et al. Conceptual Design
Installation
Observatory Facilities
14 Jan 2015
D1002847-v1 aLigo Installation, LLO Corner Station, Cartridge + Cleanroom, Layout John Worden et al. Installation
Observatory Facilities
14 Jan 2015
D1003142-x0 Rack and Cable Tray Layouts Dennis Coyne System Engineering
Observatory Facilities
14 Jan 2015
C1400943-v1 SOW LIGO Hanford DCS Computer Room Air Conditioning John Worden Procurements
Observatory Facilities
07 Oct 2014
D1400304-v1 LHO DCS Facility HVAC Plan and Sections John Worden Observatory Facilities
30 Sep 2014
D1400305-v1 LHO DCS Facility Reflected Ceiling Plan John Worden Observatory Facilities
30 Sep 2014
D1400306-v1 LHO DCS Facility Curtain Plan and Details John Worden Observatory Facilities
30 Sep 2014
D1400307-v1 LHO DCS Facility Schedules, Notes, and Details John Worden Observatory Facilities
30 Sep 2014
D1400308-v1 LHO DCS Facility Electrical/Data Site Plan John Worden Observatory Facilities
30 Sep 2014
G1000125-v9 aLIGO BSC-ISI, HAM-ISI, and HEPI Basis and Naming Conventions Jeffrey Kissel et al. Vacuum
Installation
Observatory Facilities
Seismic Isolation
18 Jun 2014
G1000552-v8 aLIGO DC Power Distribution Racks etal David Kinzel Installation
Observatory Facilities
13 May 2014
G1301067-v1 PEM update, September 2013 Robert Schofield Observatory Facilities
07 Mar 2014
D1400007-v1 aLIGO DC Breaker Switch Box Benjamin Abbott Observatory Facilities
15 Jan 2014
C1302049-v3 Statement of Work for insulation removal at LHO John Worden Vacuum
Procurements
Observatory Facilities
26 Aug 2013
G1300119-v2 Friendly Power Shutdown for LLO Corner Buildings David Kinzel Vacuum
System Engineering
Data and Computing
Commissioning
Laser Systems
Input Optics
Core Optics
Data Acquisition System
Sensing and Control
Auxiliary Optics
Observatory Facilities
Suspensions
Seismic Isolation
Policies
11 Apr 2013
D1201231-v5 LLO Rack & Cable Tray Layout, Y-End, BSC5-L1 Kurt Buckland et al. System Engineering
Observatory Facilities
18 Mar 2013
C1300165-v1 Specification for Installation WA and LA LIGO Site Carol Wilkinson Procurements
Installation
Observatory Facilities
24 Jan 2013
D1002842-v1 aLIGO Installation, LLO X-End Station, Cartridge & Cleanroom, Layout Brian O'Reilly et al. Installation
Observatory Facilities
18 Dec 2012
D1201025-v1 Strain Relief Clip for DC Power Supply Shelves David Kinzel Installation
Observatory Facilities
18 Jul 2012
G1200555-v2 LAE and Enclosures Access Discussion David Kinzel et al. Laser Systems
Installation
Observatory Facilities
Safety
01 Jun 2012
E080462-v1 Infrasonic Microphone and PEM++ Gabor Szeifert et al. Conceptual Design
System Test
Data and Computing
Other data analysis
Requirements
Data quality / vetoes
Data Acquisition System
Fabrication
Basic R&D
Computing/archiving
Integration
Upgrades
Sensing and Control
Preliminary Design
Observatory Facilities
Calibration
01 Apr 2012
E030647-v1 Advanced LIGO Detector System Interface Control Document (ICD) Dennis Coyne Vacuum
System Engineering
Data and Computing
Laser Systems
Input Optics
Core Optics
Data Acquisition System
Sensing and Control
Auxiliary Optics
Final Design
Observatory Facilities
Suspensions
Seismic Isolation
01 Apr 2012
D970210-v2 ASC Monument Locations-Washington Site Hugh Radkins et al. System Engineering
Installation
Observatory Facilities
21 Mar 2012
C1200346-v2 SOW LIGO Hanford H1 Electronics Air Conditioning John Worden Procurements
Observatory Facilities
17 Jan 2012
D1200028-v1 LIGO H1 Electronics HVAC Plan John Worden Procurements
Observatory Facilities
17 Jan 2012
D1200029-v1 LIGO H1 Electronics HVAC Plan and Equipment Schedules John Worden Procurements
Observatory Facilities
17 Jan 2012
D070125-v3 LHO CDS Lans and Gateways David Barker Installation
Observatory Facilities
29 Nov 2011
C1106855-v1 LHO Landscaping Photos - Tumbleweeds John Worden Operations Business
Observatory Facilities
25 Oct 2011
C1106854-v1 LHO Landscaping Photos John Worden Operations Business
Observatory Facilities
25 Oct 2011
M990034-v2 OBSOLETE Richard Savage et al. Operations
Observatory Facilities
Policies
01 Aug 2011
D1002926-v2 Module-E, BSC Cartridge installation, aLIGO Sam Barnum et al. Installation
Observatory Facilities
15 Jun 2011
C1104440-v2 Statement or Work for H2 Electronics Building HVAC John Worden Procurements
Observatory Facilities
02 Jun 2011
M060056-v2 Advanced LIGO Reference Design David Shoemaker Conceptual Design
Reports
Detector
08 May 2011
G1100469-v3 FMP Technical - NSF review April2011 John Worden Observatory Facilities
05 May 2011
E1100385-v2 Cable Lengths, End Station, H1 & H2 Dennis Coyne System Engineering
Observatory Facilities
21 Apr 2011
E1000760-v2 Cable Lengths, Corner Station, H1 & H2 Dennis Coyne System Engineering
Observatory Facilities
12 Jan 2011
C1002822-v1 SOW for FM-150b H2 Electronics Building Alan Wilkins Procurements
Observatory Facilities
22 Dec 2010
C1002079-v1 Specification for De-Installation LA LIGO Site LSC Requirements
Observatory Facilities
11 Nov 2010
C1001836-v1 Specification for De-Installation - Washington site. John Worden et al. Procurements
Installation
Observatory Facilities
11 Nov 2010
D0902637-v1 LLO Vacuum Bake Oven Lid Cart Michael Meyer Final Design
Observatory Facilities
12 Apr 2010
D0902107-v1 Vacuum Bell Jar Saddle Michael Meyer Final Design
Observatory Facilities
12 Apr 2010
E0900485-x0 Document Change Notice (DCN) - LLO Vacuum Chamber Fixtures Michael Meyer Final Design
Observatory Facilities
23 Feb 2010
D1000190-x0 Pod Testing Vacuum Chamber Cart Michael Meyer Preliminary Design
Observatory Facilities
28 Jan 2010
D080366-v2 Viewport Guard Shield Michael Meyer Vacuum
Final Design
Observatory Facilities
24 Jan 2010
T0900637-v1 Fan Gasket for LLO Rack 6 David Kinzel Conceptual Design
Observatory Facilities
16 Dec 2009
D0902638-x0 LLO Vacuum Bake Oven Lid Cart Assembly Michael Meyer Preliminary Design
Observatory Facilities
09 Nov 2009
D0902181-x0 Foil Holder Top Plate Michael Meyer Final Design
Observatory Facilities
24 Sep 2009
D0901576-v1 Foil Holder Assembly Michael Meyer Preliminary Design
Observatory Facilities
21 Aug 2009
D0901572-v1 Foil Holder Base Plate Michael Meyer Preliminary Design
Observatory Facilities
21 Aug 2009
D0901573-v1 Foil Holder Vertical Support Michael Meyer Preliminary Design
Observatory Facilities
21 Aug 2009
D0901574-v1 Foil Holder Horizontal Support Michael Meyer Preliminary Design
Observatory Facilities
21 Aug 2009
D0901575-v1 Foil Holder Rod Michael Meyer Preliminary Design
Observatory Facilities
21 Aug 2009
D0901785-v1 Foil Holder - Roll Stop Michael Meyer Preliminary Design
Observatory Facilities
21 Aug 2009
E080529-v1 LIGO Aqueous Parts Washer Betsy Weaver Observatory Facilities
24 Mar 2009

Number of documents found: 115


DCC Version 3.4.2, contact Document Database Administrators